April 14, 2020 Progress Video
-
December 2020
- Dec 9, 2020 CoWorking Paint Dec 9, 2020
-
November 2020
- Nov 20, 2020 B East IP Nov 20, 2020
- Nov 3, 2020 B Heat Pump Set Nov 3, 2020
-
October 2020
- Oct 20, 2020 Micro Unit Millwork Divider Oct 20, 2020
- Oct 8, 2020 Co-working Roof Oct 8, 2020
-
September 2020
- Sep 22, 2020 GFRC Up 6 Floors Sep 22, 2020
- Sep 9, 2020 A Roof Started Sep 9, 2020
-
August 2020
- Aug 26, 2020 B Rooftop Mechanical Aug 26, 2020
- Aug 11, 2020 B Resi Skin Getting Close Aug 11, 2020
-
July 2020
- Jul 27, 2020 Framing to Parapet Jul 27, 2020
- Jul 7, 2020 Roof Deck Complete Jul 7, 2020
-
June 2020
- Jun 25, 2020 Vinyl Windows Up 4 Levels Jun 25, 2020
- Jun 18, 2020 A Roof Deck Installing Jun 18, 2020
- Jun 9, 2020 Skin Started on B Jun 9, 2020
- Jun 2, 2020 CoWorking Top Level Slab Pour Jun 2, 2020
-
May 2020
- May 26, 2020 Top Floor Structural Started May 26, 2020
- May 20, 2020 Infinity Complete May 20, 2020
-
April 2020
- Apr 29, 2020 Building B Wood Roof Complete Apr 29, 2020
- Apr 22, 2020 6th Infinity Level Apr 22, 2020
- Apr 14, 2020 Building B Roof Apr 14, 2020
- Apr 8, 2020 5th Infinity Level Apr 8, 2020
- Apr 1, 2020 Exterior Sheathing Apr 1, 2020
-
March 2020
- Mar 23, 2020 CoWorking 2 Levels of Decking Mar 23, 2020
- Mar 16, 2020 4th Infinity Level Mar 16, 2020
-
February 2020
- Feb 25, 2020 CoWorking Steel Feb 25, 2020
- Feb 13, 2020 3rd Infinity Level Feb 13, 2020
-
January 2020
- Jan 29, 2020 2nd Level of Infinity Jan 29, 2020
- Jan 15, 2020 Building B Framing Jan 15, 2020
-
December 2019
- Dec 17, 2019 Infinity System Started Dec 17, 2019
- Dec 5, 2019 Another Transfer Slab Pour Dec 5, 2019
-
November 2019
- Nov 21, 2019 1st Transfer Slab Pour Nov 21, 2019
- Nov 6, 2019 Shoring Started for Transfer Slab Nov 6, 2019
-
October 2019
- Oct 25, 2019 360 Yard Pour Oct 25, 2019
- Oct 8, 2019 B Elevator Pour Oct 8, 2019
-
September 2019
- Sep 25, 2019 Curved Ramp Wall Form Sep 25, 2019
- Sep 5, 2019 Building B Footing Ex Sep 5, 2019
-
August 2019
- Aug 19, 2019 Elevator Towers Aug 19, 2019
-
July 2019
- Jul 3, 2019 Building B Demo Jul 3, 2019
-
June 2019
- Jun 19, 2019 Northeast Concrete Pour Jun 19, 2019
- Jun 5, 2019 Waterproofing & Rebar Jun 5, 2019
-
May 2019
- May 24, 2019 Waterproofing May 24, 2019
- May 8, 2019 Ex Continues May 8, 2019
-
April 2019
- Apr 25, 2019 Rat Slab Apr 25, 2019
- Apr 8, 2019 Excavation Apr 8, 2019
-
March 2019
- Mar 26, 2019 Excavation Started on A Mar 26, 2019
- Mar 11, 2019 Barnes Clean Up Mar 11, 2019
-
February 2019
- Feb 27, 2019 Barnes Demo Feb 27, 2019
-
January 2019
- Jan 23, 2019 Pre Construction Jan 23, 2019
-
January 2017
- Jan 14, 2017 RFP Jan 14, 2017